Stacks Image 33132

A Community Working Together to Build a Better Somerville High School

The City of Somerville is building a new Somerville High School at the site of the existing one, using funds obtained locally and through a grant by the Massachusetts School Building Authority. The new campus will provide a state-of-the-art, innovative, and nurturing learning environment to SHS students for decades to come, and will serve as a premier community resource and gathering space.
Stacks Image 31701
Above: View a flyover rendering of the proposed Somerville High School redesign plans.

Check Back Frequently for Project Updates

New information will be added to this site on an ongoing basis.
  • Construction Impacts and Updates
    Updated 7/12/2019
    • The E building (furthest east, in front of the gym) is coming down. Demo is expected to continue over the course of the week of July 15.
    • Suffolk continues erecting structural steel at the western new building.
  • FAQs
    What is the project timeline?

    1. Phase 1 New Building West Construction: April 2018 to August 2019
    2. Phase 2 New Building East Construction: June 2019 to August 2020
    3. Phase 3 Demolition & Site Improvements: June 2020 to May 2021


    How can I stay informed about the construction timeline and impacts?


    The City maintains a biweekly email update group for residents and businesses. To sign up, email JRossetti@somervillema.gov. Parents and guardians of current Somerville High School students and rising freshmen will receive regular project updates via email and/or voicemail from the District.
  • Construction Camera Feed
  • June 2019

    Phase 1 Structural Steel Installation

    Click on an image to enlarge it:
     
  • May 2019

    Gym Roof Reconstruction

    Click on an image to enlarge it:
     
  • March 2019

    Foundation Wall Construction

    Stacks Image 33574
  • February 2019

    Foundations Begin

  • January – February 2019

    Soil Nail Wall Installation

    Stacks Image 33458
  • November 2018 – February 2019

    Central Hill Monument Relocation

    Stacks Image 33463
  • October 2018 – February 2019

    Soil Excavation & Export

    Stacks Image 33468
  • September 2018

    Debris Removal

    Stacks Image 33473
  • June – August 2018

    East 1929 Classroom Wing Demolition & Abatement

    Stacks Image 33478